Project Summary

  • Client: Jabatan Kemajuan Orang Asli Malaysia (JAKOA)
  • Implementation: Conventional
  • Terrain: Flat
  • Duration: 2013 - 2014
  • Project Cost: 5 Million (MYR)
  • Status: Completed

Project Information

Located in a rural area of Perak, the proposed project is to install and supply treated water for Orang Asli at four different villages which is Kampung Gesau, Kg Penderas, Kg Rasau and Kg Tibang. The project consist of the water pipeline, water storage tank and water reticulation system for the villages. The scope of work covers all infrastructure related design works from conceptual design until design support during construction.